If 20 people finish the job in 12 days, in how many days 6 people can finish the same job?

Your Answer has been submitted. The content will appear here after approval.
Please wait while your Answer is being submitted...

Your Answer has been submitted. The content will appear here after approval.
Please wait while your Answer is being submitted...
Answers
1 Answers

Learning Pundits Content Team
Let x be the number of days taken by 6 people. With more number of people working, the job will take less time to be completed. That means they are inversely proportional.
- People Days
- 20 12
- 6 x
That is 20 × 12 = 6x or x = (20 × 12)/6
x = 40
Hence, 6 people can finish the job in 40 days.